• We have begun redevelopment work in earnest on Bronte, which has a nine week program. We start with demolition of the intrusive toilet block and then move to construction of new toilets and the kitchen, along with all interior finishes. Roof painting and plumbing has moved to the northern wing now that we have space to erect the scaffolding.
• Electrical and mechanical services are also being installed in Bronte and the Barracks in parallel with this work.
• Landscape works are drawing to a close. Scheduling of landscape works in the Bronte courtyard is dependent upon how the construction work progresses, but should occur during the last couple of weeks of this month. The Avenue pedestrian apron has been laid. Fencing issues should be resolved soon, and then work started.
• Interior finishes are being applied in The Barracks south wing, along with various little tasks around the veranda and external envelope of the building.
Basically, the major works within Bronte are underway and we are also progressing the many little ‘final’
tasks to do across the precinct.

Thanks
Brett